Construction Update and Picture of the Week
Last weekend, FTC crews successfully shifted about 2,000 feet of freight track and cut-over from Pasadena Ave. to San Gabriel…
Last weekend, FTC crews successfully shifted about 2,000 feet of freight track and cut-over from Pasadena Ave. to San Gabriel…
The Construction Authority has upgraded our website to provide more detailed information about on-going construction activities and how they might…
Click on the image above to watch Construction Authority CEO Habib F. Balian as he provides a project update on…
The Construction Authority Board of Directors will be holding a meeting on Wednesday, March 20, 2013 at at 7:00 p.m….
Demolition of the old 700-ft long single-track San Gabriel River Bridge is now underway. See the progress crews made in…
Work on the Highland Ave crossing in Duarte is nearly complete. The road re-opened to traffic earlier this week.
This article originally appeared in the LA Daily News website on 3/11/2013. More people taking public transportation, L.A.’s Metro system…
Crews set the first sets of track and ties near the future Azusa-Alameda Station. Other Reminders: Palm Dr – CLOSED…
The following blog post originally appeared on The Source on March 7, 2013. Foothill Extension Construction Authority approves routes for…
This post originally appeared in the Curbed LA Blog on March 4, 2013. Don’t Give Up on Gold Line to…