VIDEO: Foothill Gold Line Project Update Highlights – July 2022
The July 2022 Foothill Gold Line project update highlights video is now available. Highlights over the past month include construction…
This past Friday, the Construction Authority held a press conference to celebrate the 9.1-mile, four-station Foothill Gold Line light rail...
Read more Twitter FacebookThe July 2022 Foothill Gold Line project update highlights video is now available. Highlights over the past month include construction…
This week, a 2,000-foot-long rail delivery train arrived at the project and dropped off rail sticks (each 1,600 feet long)…
Crews this week are placing forms and pouring concrete for curbs, gutters and medians for the newly aligned roadways at…
Utilizing a make-shift “rail train,” crews this week delivered rail sticks (each approximately 800 feet long) along the corridor to…
Crews this week utilized a one-night closure of Route 66 in Glendora to successfully complete the second major concrete pour…
Crews are constructing the super-structure of the new light rail bridge over Lone Hill Ave. in Glendora. To learn more…
Crews this week installed two new light rail tracks at the San Dimas Canyon Rd. crossing in San Dimas/La Verne….
As you may have read, the 9.1-mile, four-station project segment from Glendora to Pomona officially reached 50% construction completion last…