Construction Update and Pictures of the Week
Crews have begun work to connect the existing Metro A Line with the newly-constructed light rail track system from Glendora…
Crews have begun work to connect the existing Metro A Line with the newly-constructed light rail track system from Glendora…
The San Dimas station artist team of Eugene and Anne Olsen Daub continue to make progress on their “walking stick”…
Crews this week continued installation of the canopy structures at the future La Verne station.
This month, crews are conducting testing of the newly-installed crossing safety equipment, gates and signals at the reconstructed grade crossings…
Blue McRight, the city-selected artist for the La Verne station, has begun creating a set of three ten-foot-tall sculptures that…
Crews are installing vehicle detection loops as part of the safety upgrades at all 21 at-grade crossings. If the loops…
The Glendora to Pomona project segment is now 82% complete overall and just about 10 months away from substantial completion,…
With the canopy columns in place, crews are now installing the canopy frames at the future La Verne station.
Crews are installing the canopy columns at the future La Verne station.
Crews are delivering the station canopy pieces to the future La Verne station for installation.
Crews continue to install the overhead catenary system (OCS) poles for the light rail system. Once complete, 350 OCS poles…
Crews are installing the overhead catenary system wires at the future La Verne station. The overhead wires will provide power…