Construction Update and Picture of the Week

Last weekend, FTC crews successfully shifted about 2,000 feet of freight track and cut-over from Pasadena Ave. to San Gabriel Ave. in Azusa. The work – which had to be completed in one weekend – included track demolition, shifting and tie-in, surfacing, signal re-installation and track inspection. Trains began running again on Monday, as shown here.