Construction Update and Pictures of the Week

Now in the second of the four-phase plan to reconfigure the Bonita Ave./Cataract Ave. intersection in San Dimas, traffic has shifted onto the new eastbound lanes on Bonita Ave., allowing crews to begin work on the foundations for the future light rail bridge without having to close lanes or streets during this phase of work.

To learn of future construction activities that may impact you, sign up for Construction Alerts or view construction activities on an interactive map at foothillgoldline.org.