Construction Update and Picture of the Week
Last weekend, FTC crews successfully shifted about 2,000 feet of freight track and cut-over from Pasadena Ave. to San Gabriel…
Last weekend, FTC crews successfully shifted about 2,000 feet of freight track and cut-over from Pasadena Ave. to San Gabriel…
The Construction Authority has upgraded our website to provide more detailed information about on-going construction activities and how they might…
Work on the Highland Ave crossing in Duarte is nearly complete. The road re-opened to traffic earlier this week.
This article originally appeared in the LA Daily News website on 3/11/2013. More people taking public transportation, L.A.’s Metro system…
The following blog post originally appeared on The Source on March 7, 2013. Foothill Extension Construction Authority approves routes for…
This post originally appeared in the Curbed LA Blog on March 4, 2013. Don’t Give Up on Gold Line to…
FTC crews move forward with third party utility relocation near the future Azusa-Alameda Gold Line station. REMINDER: Foothill Blvd (between…
Work at the Gold Line Operations Campus continues as crews install shoring columns for the facility’s north retaining wall.
FTC crews continue work at Colorado Blvd in Arcadia, where a new dual-track light rail bridge is under construction. REMINDER:…
Below is a recap of some of the articles and posts written about the Gold Line Bridge since its completion…