Foothill Gold Line: First project — think water and sewer lines — completed ahead of schedule – Pasadena Star-News/San Gabriel Valley Tribune/Inland Valley Daily Bulletin

gold-line-glendora-to-montclair-map-1

By Liset Marquez

August 21, 2018

[Excerpt]:

The project that will extend the Foothill Gold Line from Glendora to Montclair has reached its first milestone – to relocate utilities along the future route – ahead of schedule.

The 12.3-mile extension is currently estimated to cost $1.5 billion and has been funded on the Los Angeles County side by Measure M sales tax dollars, approved by voters in November 2016.

For the past 11 months, crews worked to relocate a dozen water and sewer lines that cross the railroad corridor, Metro Gold Line Foothill Extension Construction Authority CEO Habib F. Balian said in a news release.

“The utility work went very smoothly and was completed two months ahead of schedule,” Balian said in the statement.

To read the full article, click here.