Construction Update and Pictures of the Week
Crews are nearing completion on installing the falsework for the future light rail bridge over the Bonita Ave./Cataract Ave. intersection…
Crews are nearing completion on installing the falsework for the future light rail bridge over the Bonita Ave./Cataract Ave. intersection…
Crews continue to construct the columns for the future light rail bridge over Route 66 in Glendora. To learn of…
Crews have begun constructing the foundations for the west abutment of the future light rail bridge over the Foothill Blvd./Grand…
Crews have started constructing the falsework for the future light rail bridge over the Bonita Ave./Cataract Ave. intersection in San…
Crews recently removed the forms for the east abutment of the future light rail bridge over Lone Hill Ave. in…
Crews this week utilized a three-day closure of the Foothill Blvd./Grand Ave. intersection in Glendora to successfully remove the existing…
Crews have started building the platform for the future Glendora station. The station will be a center platform station. Soon…
Last week, crews successfully completed the relocation of the freight track and underground utility work at the San Dimas Canyon…
This past weekend, crews completed the installation of the two column foundations for the future light rail bridge over Route…
After three months of reconstruction work, D St. in La Verne reopened to motorists and pedestrians this past Friday. To…
The November 2021 Foothill Gold Line project update highlights video is now available. Highlights include numerous bridge work underway in…
Earlier this week, crews completed the installation of the foundations for the two columns for the future light rail bridge…