Foothill Transit Constructors has begun removing the old, freight rail track from the right-of-way. They have started in the city…
Foothill Transit Constructors has begun removing the old, freight rail track from the right-of-way. They have started in the city…
This past week crews continued installation of the reinforcing steel inside of the form-work, in preparation for the major concrete…
The I-210 Bridge formwork is almost ready for concrete. The architectural form-liners are nearly all in place and reinforcing steel…
Crews install rubber form liner along the inside walls of the structure. These elements of the form are what will…
From the vantage point of the new walkway built above the superstructure, it is easy to see the significant progress…
The crew has been hard at work installing the formwork for the bridge superstructure. Here you see how the installed…
Our new Construction Update Video: April-June 2012 is almost ready to launch. Look out for it next week on IWillRide.
An eastbound shot of the completed falsework for the I-210 Gold Line Bridge. Work is now underway on the formwork…
This week, the last of the false-work beams are being installed across the eastbound lanes of the I-210 Freeway. Each…
Kiewit Parsons Joint Venture crews conduct geotechnical investigations at the San Gabriel River in Irwindale where the San Gabriel River…
Crews install falsework supports for the I-210 Gold Line Bridge which will create a safe work space over the lanes…
This week 21 trucks lined up to pour nearly 227 cubic yards of concrete for the walls of the southern…