Construction Update and Picture of the Week
Crews continue to install the form work for the southern bridge abutment. Late next week, crews are scheduled to pour…
Crews continue to install the form work for the southern bridge abutment. Late next week, crews are scheduled to pour…
This photo was taken from the perspective of the artist rendering. You can now start to see the main elements…
The third and final column was completed this week. This photo shows the crew successfully removing the form, after it…
The two main column structures in the center median of the I-210 Freeway are now complete and the “form” was…
The column “form” is nearly installed on the first of three main columns. Once complete, concrete will be poured into the…
Crews installed the first of 18 foundations this week. These 50-foot deep, three-foot diameter reinforced foundations will support the future…
18-foot tall shoring plates were installed this week to temporarily retain surrounding earth from falling into the construction site as…
Crews this week continued demolition activities on the 40 year old abutments.
With the relocation of the storm water drainage pipe and demolition of the old bridge’s foundation finalized, the construction team…
Crews continue demo work on old bridge’s foundation and commence work on building a new drainage system. In the coming…
Many of you have seen the steel cages sticking out of the completed deep foundations as you head eastbound on…
By the end of the week, all three of the deep foundations will be complete. Want to know what’s next…