VIDEO: Foothill Gold Line Project Update Highlights – September 2020
Crews are now actively reconstructing three railroad crossings along the corridor: Barranca Ave. and Glendora Ave. in Glendora, and Gladstone…
Crews are now actively reconstructing three railroad crossings along the corridor: Barranca Ave. and Glendora Ave. in Glendora, and Gladstone…
SoCalGas crews are currently out at Glendora Ave. relocating and protecting the underground gas line. To learn of future construction…
Crews at Glendora Ave. and Gladstone St. this week are installing underground conduit to house and protect the communication lines…
This week, a rail delivery train dropped off steel rail at various locations along the project corridor to be used…
Crews this week began demolishing the roadway, medians, curbs, gutters and sidewalk on Barranca Ave. at the railroad crossing in…
Crews today began demolishing the roadway, medians, curbs, gutters and sidewalks, as well as removing the unused southern freight tracks,…
Crews this week continue to make progress relocating and protecting underground utilities at the Gladstone St. railroad crossing in San…
To make room for the light rail system, crews this week began removing overhead power lines that run the length…
SoCalGas crews are nearing completion to protect and relocate the underground gas line at the Barranca Ave grade crossing in…
Crews this week are relocating and protecting underground utilities at the Gladstone St. railroad crossing in San Dimas. To learn…
Crews this week demolished the roadway, medians, curbs, gutters and sidewalks on Gladstone St. at the railroad crossing in San…
After months of preparations, coordination and design work, KPJV is now set to begin major construction on the Glendora to…