Construction Update and Pictures of the Week
Crews are installing sound walls atop the west approach for the new Foothill Blvd./Grand Ave. light rail bridge in Glendora….
Crews are installing sound walls atop the west approach for the new Foothill Blvd./Grand Ave. light rail bridge in Glendora….
At an off-site location, crews are fabricating the canopy frames for the future San Dimas station. 📆 JOIN US: On…
The 9.1-mile, four-station Foothill Gold Line from Glendora to Pomona is now 71% complete! Watch the latest highlight video below…
Crews have completed installing the canopy frames for the future Glendora station. 📆 JOIN US: On June 24, 2023, the…
Crews are installing the light rail tracks on the new light rail bridge over Lone Hill Ave. in Glendora. 📆…
Eugene Daub and Anne Olsen Daub, the city-selected artist team for the San Dimas station, this week showed off a…
Crews are installing the canopies for the future Glendora station. To learn of future construction activities that may impact you,…
Crews are installing the overhead catenary system wires that will provide power for the future light rail trains. The train…
Crews this week installed the eighth and final traction power substation (TPSS) for the Glendora to Pomona project. Each TPSS…
Crews are pouring concrete for the platform deck of the future Pomona station. To learn of future construction activities that…
Crews are installing the light rail tracks on the new light rail bridge over the Foothill Blvd./Grand Ave. intersection in…
Crews this week completed the work necessary to reopen the Garey Ave. crossing in Pomona to motorists and pedestrians. Crews…