Construction Update and Pictures of the Week
Crews are nearing completion on the first of four construction phases needed to reconfigure the Bonita Ave./Cataract Ave. intersection in…
Crews are nearing completion on the first of four construction phases needed to reconfigure the Bonita Ave./Cataract Ave. intersection in…
Crews this week installed the eastbound light rail track at the Eucla Ave. grade crossing in San Dimas. Track installation…
Crews this week installed the westbound light rail track and relocated freight track at the Eucla Ave. grade crossing in…
Just east of the Gladstone St. grade crossing in San Dimas, crews are constructing new walls along the corridor that…
Ahead of freight service resuming in early June, crews are nearing completion on relocating approximately five miles of freight track…
Click here or below to watch the May 2021 highlight video of the activities over the past month on the…
At the Glendora Station, crews have installed the relocated freight track over the pedestrian undercrossing. Future riders will be able…
After beginning reconstruction in early March, Elwood Ave. in Glendora reopened to motorists and pedestrians today – one month ahead…
Starting on Monday evening and continuing through Thursday night, crews worked around the clock this week at the Lone Hill…
After three months of reconstruction work, Fulton Rd. in La Verne/Pomona was reopened to motorists and pedestrians this week (including…
This week, following the successful demolition of the old bridge over Big Dalton Wash in Glendora, crews installed five concrete…
Click here or below to watch the April 2021 highlight video of the activities over the past month on the…