Construction Update and Pictures of the Week
Crews have installed the two relocated freight tracks (one main track and one siding track) at the Garey Ave. crossing…
Crews have installed the two relocated freight tracks (one main track and one siding track) at the Garey Ave. crossing…
Crews are installing the light rail tracks on the new light rail bridge over the Bonita Ave./Cataract Ave. intersection in…
Crews this week began installing the overhead catenary system (OCS) poles onto foundations built about every 200 feet along the…
Crews are constructing the walls for the future Pomona station platform. To learn of future construction activities that may impact…
Crews this week began the full reconstruction of the Garey Ave. grade crossing in Pomona. It is the last of…
Crews have successfully removed all of the falsework that was supporting the newly-completed light rail bridge over Lone Hill Ave….
Watch the January 2023 project update video below to see the latest activities over the past month. Highlights include the…
With the underground utility work completed, crews have begun constructing the platform for the future Pomona station. To learn of…
Crews are utilizing nightly full closures of Lone Hill Ave. in Glendora to remove the falsework for the newly-completed light…
At an off-site location, fabrication continues on the canopies for the future Glendora station. To learn of future construction activities…
Crews are installing sound walls at the site of the future San Dimas station. About 28,000 ft. of sound walls…
As 2022 comes to an end, the 9.1-mile, four-station Foothill Gold Line light rail project from Glendora to Pomona is…