Construction Update and Pictures of the Week
Crews are now constructing the west abutment (the support at the end of the bridge) for the new light rail…
Crews are now constructing the west abutment (the support at the end of the bridge) for the new light rail…
Crews installed five concrete girders for a new light rail bridge over Live Oak Wash in La Verne. To learn of future…
Crews are now constructing the east abutment (the support at the end of the bridge) for the new light rail…
The September 2021 Foothill Gold Line project update highlights video is now available. Highlights include the 2,000-foot-long rail delivery train;…
After five months of reconstruction work, Vermont Ave. in Glendora reopened to motorists and pedestrians today. NOTE: West Ada Ave….
Crews this week installed the eastbound and westbound light rail tracks at the Vermont Ave. grade crossing in Glendora. To…
After nearly four months of reconstruction work, Loraine Ave. in Glendora reopened to motorists and pedestrians this past weekend. To…
Crews this week successfully installed four concrete girders for the new light rail bridge structure over San Dimas Wash in…
This week, a rail delivery train dropped off 1,600-foot-long rail pieces at various locations along the project corridor from Glendora…
Crews this week are installing the eastbound light rail track and constructing the new medians and curbs at the Loraine…
The Foothill Gold Line from Glendora to Pomona is now more than one-third complete overall. Click here or below to…
After four months of reconstruction work, E St. in La Verne was reopened to motorists and pedestrians this past Monday….