Construction Update and Picture of the Week
Construction Authority CEO, Habib F. Balian leads a tour of the 24-acre, $265 million Gold line Operations Campus for Metro…
Construction Authority CEO, Habib F. Balian leads a tour of the 24-acre, $265 million Gold line Operations Campus for Metro…
Crews install reinforcing steel for the side-platform foundation walls at the Monrovia station.
Fasching’s Car Wash (located on the corner of Santa Anita Ave and Colorado Blvd, Arcadia) owner George Fasching makes the…
This week crews installed ten 88-foot long, 100,000 pound steel reinforced concrete girders on top of the Colorado Blvd bridge…
Crews grade the area at the future Arcadia station in anticipation of beginning work on the platform foundations.
Palm Drive in Azusa re-opened to pedestrian and vehicular traffic this week after being closed four months for construction of…
Construction of the 24-acre Gold Line Operations Campus is moving along rapidly. As shown in this aerial photo, underground utilities…
Work is underway on more than a dozen bridges along the 11.5-mile corridor. The abutment walls are nearing completion on…
Underground utility work continues at the California Ave crossing in Monrovia. Reminder: California Ave. (just north of Duarte Rd.) will…
Crews begin demolition of the Santa Anita Wash bridge in Monrovia, one of 24 bridges along the 11.5-mile Foothill Extension…
Last weekend, FTC crews successfully shifted about 2,000 feet of freight track and cut-over from Pasadena Ave. to San Gabriel…
Demolition of the old 700-ft long single-track San Gabriel River Bridge is now underway. See the progress crews made in…