Construction Update and Picture of the Week
An eastbound shot of the completed falsework for the I-210 Gold Line Bridge. Work is now underway on the formwork…
An eastbound shot of the completed falsework for the I-210 Gold Line Bridge. Work is now underway on the formwork…
This week, the last of the false-work beams are being installed across the eastbound lanes of the I-210 Freeway. Each…
Kiewit Parsons Joint Venture crews conduct geotechnical investigations at the San Gabriel River in Irwindale where the San Gabriel River…
Crews install falsework supports for the I-210 Gold Line Bridge which will create a safe work space over the lanes…
This week 21 trucks lined up to pour nearly 227 cubic yards of concrete for the walls of the southern…
Crews continue to install the form work for the southern bridge abutment. Late next week, crews are scheduled to pour…
This photo was taken from the perspective of the artist rendering. You can now start to see the main elements…
The third and final column was completed this week. This photo shows the crew successfully removing the form, after it…
The two main column structures in the center median of the I-210 Freeway are now complete and the “form” was…
The column “form” is nearly installed on the first of three main columns. Once complete, concrete will be poured into the…
Crews installed the first of 18 foundations this week. These 50-foot deep, three-foot diameter reinforced foundations will support the future…
18-foot tall shoring plates were installed this week to temporarily retain surrounding earth from falling into the construction site as…