Construction Update and Pictures of the Week
At the Bonita Ave./Cataract Ave. intersection in San Dimas, crews this week began constructing the eastern foundations for the future…
At the Bonita Ave./Cataract Ave. intersection in San Dimas, crews this week began constructing the eastern foundations for the future…
At the site of the future La Verne station parking facility, crews this week completed the demolition of an industrial…
Crews have started constructing retaining walls that will be part of the approaches for the future light rail bridge over…
Now in the second of the four-phase plan to reconfigure the Bonita Ave./Cataract Ave. intersection in San Dimas, traffic has…
After four months of reconstruction work, Eucla Ave. in San Dimas was reopened to motorists and pedestrians today. To learn…
Crews this week installed concrete girders for a new freight bridge over Live Oak Wash in La Verne. The freight…
Click here or below to watch the June 2021 highlight video of the activities over the past month on the…
Crews are nearing completion on the first of four construction phases needed to reconfigure the Bonita Ave./Cataract Ave. intersection in…
Crews this week installed the eastbound light rail track at the Eucla Ave. grade crossing in San Dimas. Track installation…
Crews this week installed the westbound light rail track and relocated freight track at the Eucla Ave. grade crossing in…
Just east of the Gladstone St. grade crossing in San Dimas, crews are constructing new walls along the corridor that…
Ahead of freight service resuming in early June, crews are nearing completion on relocating approximately five miles of freight track…