Gold Line Foothill Extension Awarded Millions In Federal Grants for Station Area Improvements
The Federal Transit Administration has awarded the Construction Authority $6 million in federal grant funding for design and construction of…
The Federal Transit Administration has awarded the Construction Authority $6 million in federal grant funding for design and construction of…
For safety purposes during concrete pouring operations for the last of three 110-foot deep, 11-foot diameter foundations, all eastbound lanes…
For safety purposes during installation of the reinforcing steel cage for the last of three 110-foot deep, 11-foot diameter foundations,…
Nearly two dozen at-grade crossings are planned between Pasadena and Azusa. Each is individually designed with the latest safety equipment…
Two down and one to go. Crews completed work on the second of three deep foundations this week following installation…
The Construction Authority Board of Directors will be holding a meeting today (Wednesday, September 28, 2011) at 7:00 p.m. The…
For safety purposes during installation of the reinforcing steel cage for the second of three 110-foot deep, 11-foot diameter foundations,…
Following Metro’s release of the latest crime statistics, the following story appeared in the Eagle Rock Patch: Metro Crime Stats:…
Following the 400 cubic yard concrete pour that completed the first deep foundation, crews coordinated the move of the massive…
Early this morning, work crews led by Skanska USA, relocated the 300-ton crane and large drill rig across the eastbound…
Following the successful completion of the first of three deep foundations last week, crews will mobilize all necessary equipment to…
This week crews have been hard at work completing the first of three deep foundations for the bridge. Activity this…