Construction Update and Pictures of the Week
This week, a rail delivery train dropped off 1,600-foot-long rail pieces at various locations along the project corridor from Glendora…
This week, a rail delivery train dropped off 1,600-foot-long rail pieces at various locations along the project corridor from Glendora…
Crews this week are installing the eastbound light rail track and constructing the new medians and curbs at the Loraine…
The Foothill Gold Line from Glendora to Pomona is now more than one-third complete overall. Click here or below to…
This week, the Foothill Gold Line Construction Authority (Construction Authority) announced that the 9.1-mile, four-station Foothill Gold Line light rail…
After four months of reconstruction work, E St. in La Verne was reopened to motorists and pedestrians this past Monday….
The following excerpt appeared in the Pasadena Star-News, San Gabriel Valley Tribune, Inland Valley Daily Bulletin and San Bernardino Sun…
At the Bonita Ave./Cataract Ave. intersection in San Dimas, crews this week began constructing the eastern foundations for the future…
The following excerpt appeared in the Inland Valley Daily Bulletin on August 2, 2021. To read the full article (may…
At the site of the future La Verne station parking facility, crews this week completed the demolition of an industrial…
The Summer 2021 Foothill Gold Line Project Newsletter is now available. Click here or below to learn the latest on…