Construction Update and Picture of the Week
Walls are starting to go up at the Gold Line Operations Campus.
Walls are starting to go up at the Gold Line Operations Campus.
As each of the six new Gold Line light rail stations begin to take shape, the station artists are hard…
Track installation has begun on the Gold Line Bridge over the I-210 Freeway.
The following article appeared in the Inland Valley Daily Bulletin on April 21, 2014. Gold Line being challenged on possible…
Myrtle Ave reopened to traffic on April 17, five weeks ahead of schedule.
The following Editorial appeared in the Pasadena Star-News, San Gabriel Valley Tribune, and Inland Valley Daily Bulletin on April 18,…
More than a mile of rail (in 800-foot segments) is being transported along the right-of-way across Duarte and into Monrovia…
Crews continue work on cross beam installation on one of three bridges that now cross Foothill Boulevard in Azusa. Just…
The following articles appeared in the Los Angeles Times on March 28, 2014 and March 31, 2014. Transportation advocates back…
The following article appeared in the San Gabriel Valley Tribune on March 29, 2014. The Green Way: ‘We are part…