VIDEO: Foothill Gold Line Project Update Highlights – April 2022
The April 2022 Foothill Gold Line project update highlights video is now available. Highlights include construction of the four new…
The April 2022 Foothill Gold Line project update highlights video is now available. Highlights include construction of the four new…
Crews have installed sound walls at the new light rail bridge over Live Oak Wash in La Verne. These are…
Crews have completed the center columns for the future light rail bridge over Lone Hill Ave. in Glendora, both of…
At the site of the future Glendora station parking facility, crews have completed the demolition of the vacated building to…
Crews this week completed the work necessary to reopen the Pasadena Ave. crossing in Glendora to motorists and pedestrians. To…
The March 2022 Foothill Gold Line project update highlights video is now available. Highlights include construction of the four new…
After four months of reconstruction work, crews this week were able to reopen the A St. crossing (north of Arrow…
The 1st Quarter 2022 Foothill Gold Line Project Newsletter is now available. Click here or below to learn: The latest…
Crews are now constructing the deck for the Glendora station platform. To learn of future construction activities that may impact…
Crews this week completed a seven-hour concrete pour for the internal walls of the super-structure for the new light rail…