VIDEO: Foothill Gold Line Project Update Highlights – March 2023
The Foothill Gold Line from Glendora to Pomona is now 68% complete. Watch the latest highlight video below to see…
The Foothill Gold Line from Glendora to Pomona is now 68% complete. Watch the latest highlight video below to see…
MONROVIA, Calif. – This week, the Foothill Gold Line Construction Authority (Construction Authority) announced that all grade crossing reconstruction work…
The following excerpt appeared in the San Gabriel Valley Tribune, Inland Valley Daily Bulletin and LA Daily News on March…
Crews are installing the new light rail tracks at the future San Dimas station. To learn of future construction activities…
The following excerpt appeared in the San Gabriel Valley Tribune, Inland Valley Daily Bulletin and LA Daily News on March…
Crews are installing the new light rail tracks for the future Glendora station. To learn of future construction activities that…
The following excerpt appeared in the San Gabriel Valley Tribune, Inland Valley Daily Bulletin, Pasadena Star-News and LA Daily News…
Crews this week completed back-to-back, nighttime concrete pours for the light rail track installation on the Bonita Ave./Cataract Ave. light…
The Winter 2023 Foothill Gold Line Project Update Newsletter is now available. This quarter’s newsletter takes a look at the…
Crews have installed the two relocated freight tracks (one main track and one siding track) at the Garey Ave. crossing…