Construction Update and Pictures of the Week
Crews are installing vehicle detection loops as part of the safety upgrades at all 21 at-grade crossings. If the loops…
Crews are installing vehicle detection loops as part of the safety upgrades at all 21 at-grade crossings. If the loops…
The Glendora to Pomona project segment is now 82% complete overall and just about 10 months away from substantial completion,…
With the canopy columns in place, crews are now installing the canopy frames at the future La Verne station.
Crews are installing the canopy columns at the future La Verne station.
Crews are delivering the station canopy pieces to the future La Verne station for installation.
Crews continue to install the overhead catenary system (OCS) poles for the light rail system. Once complete, 350 OCS poles…
Crews are installing the overhead catenary system wires at the future La Verne station. The overhead wires will provide power…
Crews are installing decorative, diamond-shaped shingles atop the roof of the future San Dimas station boarding canopy.
Crews are constructing the plaza area at the future Glendora station.
MONROVIA, Calif. – At their January meeting today, Claremont Council Member Ed Reece and Glendora Mayor Mendell Thompson began a…