Construction Update and Pictures of the Week
At the future Pomona station, crews are preparing the west ticketing area canopy for installation, and preparing to paint the…
At the future Pomona station, crews are preparing the west ticketing area canopy for installation, and preparing to paint the…
Crews have completed the installation of a critical safety element as they prepare to test the new light rail system…
The 9.1-mile, four-station Glendora to Pomona project segment is now 85% complete, and continues to be on time and on…
Crews are installing the canopy structures at the future Pomona station. It is the last set of station canopies to…
Foothill Gold Line and KPJV staff will be hosting information booths at community Earth Day events in Glendora (April 20)…
Crews have installed the four remaining art column structures at the plaza area of the future Glendora station (the first…
Crews have begun work to connect the existing Metro A Line with the newly-constructed light rail track system from Glendora…
The San Dimas station artist team of Eugene and Anne Olsen Daub continue to make progress on their “walking stick”…
Crews this week continued installation of the canopy structures at the future La Verne station.
This month, crews are conducting testing of the newly-installed crossing safety equipment, gates and signals at the reconstructed grade crossings…