Construction Update and Picture of the Week
Crews this week continued demolition activities on the 40 year old abutments.
Crews this week continued demolition activities on the 40 year old abutments.
With the relocation of the storm water drainage pipe and demolition of the old bridge’s foundation finalized, the construction team…
Crews continue demo work on old bridge’s foundation and commence work on building a new drainage system. In the coming…
Many of you have seen the steel cages sticking out of the completed deep foundations as you head eastbound on…
By the end of the week, all three of the deep foundations will be complete. Want to know what’s next…
Two down and one to go. Crews completed work on the second of three deep foundations this week following installation…
Following the 400 cubic yard concrete pour that completed the first deep foundation, crews coordinated the move of the massive…
This week crews have been hard at work completing the first of three deep foundations for the bridge. Activity this…
This week has seen scorching temperatures as well as heightened activity around the I-210 Bridge. Crews delivered and assembled the…